Projects

Select Projects

Bridge Over Mula- Mutha River at Balewadi

Pune Municipal Corporation & Pimpri Chinchwad Corporation is constructing a bridge at Balewadi s. no. 46/47. The cost of construction is shared 50:50% by both the corporations. The work is doing by Pune Municipal Corporation, Pune.

Length

175 R/ mtr.

Width

30 R/mtr.

Approach

24.179 (Balewadi side)

32.159 ( Wakad side)

Span

7 nos.

Construction type

Prestressed Voided Slab

(I Girder, Box Girder, Voided slab, steel structure)

Estimated amt.

Rs. 30,86,44,790/-

Technical Committee resolution no. 118 dtd. 09/01/2013.

Tender amt.

Rs. 31,45,09,041 .01 (1.09% more)

Work status

Present situation

In PMC side 12 deck slab & approach road completed & PCMC side 2 deck slabs - approach remained due to non- availability of land.

Total expenditure

15.10 Cr. (PMC side)

Benefits : Proposed construction of bridge will connect PMC & PCMC area, The shortest route will be available for citizens. After completion of bridge Balewadi & Wakad area will be developed with planning.

balewadi over bridge