Railway Over Bridge at Mundhwa

Name of work

Construiction of Railway over bridge (ROB) between s. no. 89 & 71 at Mundhwa over Pune – Solapur Railway line on 24.00 MT. HCMTR

Work order

Outward No. 3092 dtd. 21.11.2015

Technical information

Railway Over Bridge

 

a) Total Length – 194.50 MT

  • Railway Portion Length – 44.5 MT out of 194.50MT

  • Non Railway Portion Length – 150 MT out of 194.50 MT

b) Breadth –

  • Railway Portion – 18 MT

  • Non Railway Portion – 16.50 MT

c) Total Span - 7 Nos.

d) Construction Type –

  • Railway Portion – Steel Girder & Composite Structure

  • Non Railway Portion – Concrete work

Sub Structure – Pile foundation – Pile Cap-Pier shaft –Pier Cap

Super Structure - I- Girder- Deck Slab.

Time Limit

24 Months

Actual Work Start Date

21.12.2015

Current Status of work

Approx. 25% work completed.

Expected date of composition of work

20.11.2017

Advantages

  • Connect – Tadigutta chowk to Mundhwa industrial area & Solapur road

  • Available alternative road to Kharadi- Hadapsar road

  • Available alternative road to Pune Airport

  • Reduces traffic conjection on Kharadi- Hadapsar road

  • Reduces pollution of Mundhawa & Magarpatta Area.

Mundwa railway over bridge Mundwa railway over bridge